Snoqualmie Falls hydroelectric project
Comprehensive redevelopment
Fall 2009 update
- Construction on the redevelopment effort begins in September 2009 and is expected to last until mid-2014.
- Construction starts Sept. 8 at Snoqualmie Falls Park; this work requires partial or full closure of the Upper Park for about two months; Upper Park work should be finished by April 2010.
- Major upgrades and enhancements to PSE’s hydroelectric infrastructure (and to Lower Park facilities) at Snoqualmie Falls will begin in late spring 2010 and continue, in stages, into 2014.
Project overview
The Snoqualmie Falls Hydroelectric Project, built in the late 1890s, is Puget Sound Energy’s oldest power-generating operation. Although the facility is more than a century old, it still produces clean, cost-effective electricity for PSE customers. In addition, the hydroelectric project’s public park and trails are one of the Pacific Northwest’s most popular scenic destinations. Under PSE’s updated federal operating license, the utility is undertaking a major, five-year redevelopment of its Snoqualmie Falls facilities. The work entails substantial upgrades to PSE’s power-generating infrastructure and major enhancements to its public recreational facilities at Snoqualmie Falls.
For more information on public access to the park and PSE's power-generation facilities, please visit our Tours & Recreation page.
Committed to keeping you informed
PSE will provide updates to the community on key changes or developments in the construction project. Our aim is to complete the work with as little public disruption as possible.
Construction schedule
| Facility |
Begin Construction |
Finish Construction |
| Plant 1 - rebuild |
March 2010 |
June 2014 |
| Plant 2 - rebuild |
June 2010 |
June 2014 |
| Upper Park - redevelopment |
September 2009 |
April 2010 |
| Lower Park - redevelopment |
June 2010 |
June 2014 |
| Park Trail |
June 2010 |
June 2014 |
Fact sheets and newsletter
Download these PDF files for more detail on PSE's Snoqualmie Falls Hydroelectric Project.
Snoqualmie Falls Hydroelectric Project Improvement Plan
Snoqualmie Falls Hydroelectric Project Q & A
Snoqualmie Falls Hydroelectric Project Update newsletter
News Releases
PSE to close Snoqualmie Falls Park this autumn for eight weeks to perform major enhancement work (09/01/2009)