Download this One Line electrical diagram
Wild Horse One Line.dwf
(172 KB DWF)**
**Please note that this is for informational purposes at this time and is not an "as-built."
Diagram details:
-
The 50 kW solar facility near the operations center will interconnect to Circuit No.8. There will be a 34.5 kV – 480 V transformer (not shown in the drawing) that will interconnect to JB 8/2. The solar facility will interconnect into this transformer on the 480 V side.
-
The 450 kW located at Quarry 1 will interconnect at 34.5 kV on Circuit No.10 at "Pole B." PSE will supply this transformer, but installation of the transformer remains in the scope of the contractor. The interconnection details will be designed with the contractor after the award of the contract.