Skip to main content

March Windstorm Event

Thursday, March. 13, 2026 - 12 a.m.

We appreciate our customers’ patience today! Crews are working tirelessly to restore power as quickly and safely as possible, with power restored to over 95% of customers. 

Work will continue around the clock until power is restored to all customers. While field crews report significant progress, they are still encountering significant issues in Skykomish and Greenwater.   

In Skykomish, crew work is focused on the westside, where there are major points of damage on the system. Work is ongoing to make repairs. It will take into Friday to identify the rest of the damage points, and then time to fix it. This is complicated by remote terrain and heavy snow coming into the area could further slow patrols. At this point, we do not have an estimated time of restoration but anticipate it could be into the weekend. We have multiple crew resources working in the area to try to restore power as soon as possible.

In Greenwater, crews are working to restore the transmission line. While the repairs are being done on transmission, crews will start patrols on the distribution system. We do not have an estimated time of restoration until these patrols can be more fully completed.

Read more

   
alert 

Safety first. Never touch or go within 35 feet of downed power lines because they might be energized. Call PSE at 1-888-225-5773 or 911 to report problems.

Report and track power outages online

Puget Sound Energy transmission line and substation projects

Sedro #4, Phase A - Alger transmission line rebuild

2018 project updates

  • Construction is complete as of early 2018.

Project Overview

To increase electric reliability for customers in northwestern Skagit County, PSE will rebuild the existing transmission and distribution lines between Alger and Belfast. Currently, the local electric system is prone to power outages due to limited capacity and aging infrastructure. The existing poles and conductors were built in the early 1960s and need to be replaced. Rebuilding these transmission and distribution lines with new, higher capacity wire and replacing the poles will strengthen the current system and reduce the frequency of outages for our customers in the area.

As part of this project, PSE will:

  • Rebuild approximately 4 miles of an existing 115 kV transmission line by replacing the existing structures with new wood poles and new, higher capacity 115 kV conductors (wires).
  • Replace approximately 3 miles of existing single-phase distribution line with three-phase tree wire. Upgrading from single-phase to three-phase tree wire will increase both the capacity and the reliability of the system. Tree wire is a specially-coated wire that significantly reduces the frequency of tree-related outages.

In advance of construction, PSE will conduct vegetation management (brush clearing and tree trimming) throughout the existing corridor. This project is part of a larger set of improvements to be implemented over the next few years in the existing transmission line corridor.

Contact us

We welcome your questions and comments! Please contact:

Bob Parker
Project Manager
1-888-404-8773
MajorProjects@pse.com