Skip to main content

Thank you for your patience and understanding as we have battled severe weather damage for the last week. We apologize for the delay in restoring power to all of our customers and want our customers to know we are committed to restoring power as quickly and safely as possible.

The majority of customers will be restored by midnight tonight. There are pockets of complex restoration work primarily related to unstable soil, access issues, and flooding that may take longer to restore. Our crews will continue to work around the clock until the last customers are restored.

As we know more, estimated restoration times will be updated on the outage map at pse.com/outagemap.


   
alert 

Safety first. Never touch or go within 35 feet of downed power lines because they might be energized. Call PSE at 1-888-225-5773 or 911 to report problems.

Report and track power outages online

Baker River Hydroelectric Project

FERC License and Amendments

Click a document title to view the document.


Baker River Project License

FERC Order on Offer of Settlement, Issuing New License, and Dismissing Amendment Application as Moot — October 17, 2008


Baker River Project Comprehensive Settlement Agreement

Baker River Hydroelectric Project Relicensing Comprehensive Settlement Agreement — November 30, 2004

Settlement Agreement Errata — May 10, 2005

License Amendments

FERC Order Amending License — December 16, 2010

FERC Order Certifying Incremental Hydropower Generation for Production Tax Credit — December 16, 2010

FERC Errata Notice, Order Amending License — January 10, 2011