Skip to main content

As customers prepare for Thanksgiving, we’re getting ready for strong winds and power outages. We understand how difficult it is to be without power, even more so over the holiday.

Crews are currently responding to outages caused by a series of storms this week. They will stay in the field, working to restore power, as long as conditions are safe.

Late Wednesday night, we’ll open local storm bases, our Emergency Coordination Center and position crews ahead of a strong system expected to impact Whatcom, Island and Skagit Counties, with a shorter burst of intense winds across King, Pierce and Thurston counties. Crews will be prepared to respond as conditions change with incoming weather systems.

 

As we prepare for storm conditions, we encourage our customers to do the same:

  • Make sure to have emergency supplies at home and in your vehicle, such as extra batteries, flashlights, food and blankets.
  • Have a battery-powered radio ready to go.
  • Charge cell phones and mobile devices in case the power goes out.
  • Download the PSE app to track and report outages or visit pse.com/outagemap.
  • Find more preparedness tips at pse.com/storm.

 

Visit PSE’s Alerts and Advisories page for more information: pse.com/alerts.


alert 

Safety first. Never touch or go within 35 feet of downed power lines because they might be energized. Call PSE at 1-888-225-5773 or 911 to report problems.

Report and track power outages online

 

Connecting Your Energy System
to PSE's Grid

DER process, requirements, and resources for projects of all sizes

Interconnection is the process of connecting a distributed energy resource (DER) – such as solar, battery storage, hydro, or biogas generation – to PSE’s electric grid. Whether your project will serve onsite energy needs, export power to the grid, or both, interconnection helps ensure safe and reliable operation for all customers.

Below are guides and resources to help you navigate the process from application to operation. 

Installing a net metered solar or net metering-eligible solar-plus storage system? Visit the net metering page for program details, eligibility requirements, and application instructions.

Steps to apply for interconnection

From initial application submission to final commissioning, the non-net metered project interconnection process typically takes 5 to 24 months, depending on the complexity of the project.

  • Application steps

    Review the following documents:

    Prepare the following items:

    • A project site plan
    • An 8760 of the hourly estimates of expected generation for every hour of the year
    • An electrical schematic which meets the requirements listed in the Technical Requirements in PSE-TC-160.70

    Visit our online portal to complete and submit a signed interconnection application.

    Be prepared to process an ACH or Wire Transfer application fee.

  • Project sizes and application fees

    Tier 1 Tier 2 Tier 3

    Generator Size

    ≤ 25 kW

    25 – 500 kW

    ≥ 500 kW

    Application fee (non-refundable)

    $100

    $500

    $1000

  • What to expect

    10 days

    PSE will review your application for completeness. Once complete, the application will proceed to engineering studies.

    2-4 months

    Engineering studies may identify required distribution system upgrades, which the interconnection customer is responsible for, in order to interconnect to PSE. The length of this stage depends on the project’s complexity.

    10 days

    Once design is complete and approved by PSE, PSE will circulate an Interconnection Agreement for signature. Once executed, this provides Permission to Construct.

    30 days

    Once construction is complete and the project has passed inspections, PSE will schedule a commissioning test. If approved, permission to energize is provided.

    110 – 170 days Total

    The Schedule 152 timelines reflect typical durations under favorable conditions for a Tier 1 or Tier 2 project and may vary by project. Complex DER interconnections often take 12–24 months or longer, and customer-driven delays can further extend schedules.

  • Interconnection fees

    Interconnection-related fees are identified through the engineering study and commissioning tests. Final invoices for these fees are typically issued within a few months after the system begins operation. These fees are separate from the application fees described above.

  • Things to know

    • Most applications are not complete when first submitted; please gather all required documents before applying
    • Adding storage increases complexity, regardless of system size (for net metered solar + storage, visit the net metering page
    • Projects that do not meet PSE’s Technical Interconnection and Interoperability Requirements (TIIR) may require revisions, which can extend review timelines
    • Applicant responsiveness during the process can impact turn-around times
    • PSE does not facilitate the design of a customer’s system

     

  • Project Communications

    Communication at each stage of the interconnection process is primarily managed through the PowerClerk portal. Customers can also contact distributedrenewables@pse.com with questions before or after submitting an application. To help expedite responses, include the project name and DER number (e.g., DER-xxxx), if available, in the subject line of all emails to PSE.

  • New construction: What if power is not online yet

    If there is no existing power at the proposed site, a New Service application for permanent service must be completed.

    • This application should be filled out by the installer and include the electrical design
    • Include both the email of the customer responsible for construction billing and the distributedrenewables@pse.com email in the “Construction charges contact email”
    • Input applicable project notes in the “Additional Project Information” section

     

We're Here to Help

PSE is committed to helping customers successfully navigate the interconnection process. Whether you're in the early planning stages or ready to submit an application,
our team is available to provide guidance and answer questions along the way.
By planning ahead and submitting complete application materials,
you can help streamline the review process and keep your project moving forward.

Start your application today and take the next step
toward connecting your project to the PSE grid.

If you have questions before or after submitting your application, contact
distributedrenewables@pse.com or assistance

Ask an Energy Advisor
ASK AN ENERGY ADVISOR

Have questions about PSE's solar programs and how to get started? We're here to help.