Connecting Your Energy System
to PSE's Grid
DER process, requirements, and resources for projects of all sizes
Interconnection is the process of connecting a distributed energy resource (DER) – such as solar, battery storage, hydro, or biogas generation – to PSE’s electric grid. Whether your project will serve onsite energy needs, export power to the grid, or both, interconnection helps ensure safe and reliable operation for all customers.
Below are guides and resources to help you navigate the process from application to operation.
Installing a net metered solar or net metering-eligible solar-plus storage system? Visit the net metering page for program details, eligibility requirements, and application instructions.
Steps to apply for interconnection
From initial application submission to final commissioning, the non-net metered project interconnection process typically takes 5 to 24 months, depending on the complexity of the project.
-
Application steps
Review the following documents:
- The “Generator Overview of Schedule 152 Interconnection Process”
- The Technical Specifications for Small Generation Interconnections PSE-TC-160.70
- The PSE Non-Residential Electric Service Handbook
Prepare the following items:
- A project site plan
- An 8760 of the hourly estimates of expected generation for every hour of the year
- An electrical schematic which meets the requirements listed in the Technical Requirements in PSE-TC-160.70
Visit our online portal to complete and submit a signed interconnection application.
Be prepared to process an ACH or Wire Transfer application fee.
-
Project sizes and application fees
Tier 1 Tier 2 Tier 3 Generator Size
≤ 25 kW
25 – 500 kW
≥ 500 kW
Application fee (non-refundable)
$100
$500
$1000
-
What to expect
10 days
PSE will review your application for completeness. Once complete, the application will proceed to engineering studies.
2-4 months
Engineering studies may identify required distribution system upgrades, which the interconnection customer is responsible for, in order to interconnect to PSE. The length of this stage depends on the project’s complexity.
10 days
Once design is complete and approved by PSE, PSE will circulate an Interconnection Agreement for signature. Once executed, this provides Permission to Construct.
30 days
Once construction is complete and the project has passed inspections, PSE will schedule a commissioning test. If approved, permission to energize is provided.
110 – 170 days Total
The Schedule 152 timelines reflect typical durations under favorable conditions for a Tier 1 or Tier 2 project and may vary by project. Complex DER interconnections often take 12–24 months or longer, and customer-driven delays can further extend schedules.
-
Interconnection fees
Interconnection-related fees are identified through the engineering study and commissioning tests. Final invoices for these fees are typically issued within a few months after the system begins operation. These fees are separate from the application fees described above.
-
Things to know
- Most applications are not complete when first submitted; please gather all required documents before applying
- Adding storage increases complexity, regardless of system size (for net metered solar + storage, visit the net metering page
- Projects that do not meet PSE’s Technical Interconnection and Interoperability Requirements (TIIR) may require revisions, which can extend review timelines
- Applicant responsiveness during the process can impact turn-around times
- PSE does not facilitate the design of a customer’s system
-
Project Communications
Communication at each stage of the interconnection process is primarily managed through the PowerClerk portal. Customers can also contact distributedrenewables@pse.com with questions before or after submitting an application. To help expedite responses, include the project name and DER number (e.g., DER-xxxx), if available, in the subject line of all emails to PSE.
-
New construction: What if power is not online yet
If there is no existing power at the proposed site, a New Service application for permanent service must be completed.
- This application should be filled out by the installer and include the electrical design
- Include both the email of the customer responsible for construction billing and the distributedrenewables@pse.com email in the “Construction charges contact email”
- Input applicable project notes in the “Additional Project Information” section
We're Here to Help
PSE is committed to helping customers successfully navigate the interconnection process. Whether you're in the early planning stages or ready to submit an application,
our team is available to provide guidance and answer questions along the way.
By planning ahead and submitting complete application materials,
you can help streamline the review process and keep your project moving forward.
Start your application today and take the next step
toward connecting your project to the PSE grid.
If you have questions before or after submitting your application, contact
distributedrenewables@pse.com or assistance
-
Helpful resources
- General overview of Schedule 152 interconnection process
- Technical Interconnection and Interoperability Requirements PSE-TC-160.70
- State Jurisdiction Electric Generation Schedule 152 (Interconnection)
- Paper Application for Tier 2 or 3 Generator Interconnections
- Paper Application for Tier 1 Generator Interconnections
- FERC Qualifying Facility Information (for projects with a net generating capacity greater than 1000kW)
- PSE New Commercial Electric Service Application (for projects with no existing site service or with modifications to existing service)
- PSE Electric Service Handbook (for Meter Placement)
- Download the list of PSE Recommended Energy Professionals
Have questions about PSE's solar programs and how to get started? We're here to help.