Skip to main content

Thank you for your patience. We are working to restore power to customers impacted by strong winds overnight and are out in full force. We understand the stress and disruption that power outages can cause. Our crews have been working hard since the weather rolled in, and they will continue to work until all customers are restored. 

When is my power coming back on?

In addition to restoring power, we have teams in the field focused on assessing the extent of damage and what repairs need to be made. As soon as we have estimated restoration times, they will be updated at pse.com/ouagemap. We understand how difficult it is to be without power and want to assure you that our crews will stay in the field until power is restored to every customer. 

Visit PSE’s Alerts and Advisories page for more information: pse.com/alerts.


alert 

Safety first. Never touch or go within 35 feet of downed power lines because they might be energized. Call PSE at 1-888-225-5773 or 911 to report problems.

Report and track power outages online

 

Skagit and Whatcom County electric system upgrades


Phase D

  • Lake Samish Park to Bellingham (6 miles)

We began working on this segment in spring 2026.

 

Check back for project updates or contact us with questions.

Sedro Woolley

Project overview

To increase electric reliability for customers in Skagit and Whatcom counties, we are rebuilding and reconductoring approximately 25 miles of existing transmission and distribution lines between Bellingham and Sedro Woolley.

Currently, the local electric system is prone to power outages due to limited capacity and aging infrastructure. The existing poles and conductors (wires) were built in the early 1960s and need to be replaced. Rebuilding these transmission and distribution lines with new, higher capacity wire and replacing the poles will strengthen the current system and reduce the frequency of outages for our customers in the area.


The overall project work will be completed in phases

All phases of this project include replacing the existing structures with new wood poles and new, higher capacity 115 kV transmission wire. It also includes replacing distribution wire as needed.

Phase A: Complete 2017
Alger to Belfast (4 miles)

Phase B: Complete 2018
Prairie Road near Belfast to the Norlum substation in Sedro Woolley (7.5 miles)

Phase C: Complete 2025
Lake Samish Park to Alger transmission line (6 miles)

Phase D: Started spring 2026
Lake Samish Park to Bellingham (6 miles)

Phase E: TBD
Bellingham substation (0.5 miles)
Norlum substation to Sedro Woolley substation (0.5 miles)