Skagit and Whatcom County electric system upgrades
ALERT
Plan ahead for upcoming traffic impacts to I-5 from September 14 to 18.
Learn more below.
Phase D
- Lake Samish Park to Bellingham (6 miles)
We began working on this segment in spring 2026.
Project update: We will be raising overhead transmission lines and installing related electrical equipment to portions of I-5, between freeway exits 246 and 250, in Bellingham.
When: 9/14 to 9/18, during nightly work hours from 9 p.m. to 4 a.m.
What you can expect:
- This work should not impact electric service for PSE customers
- There will be nightly northbound and southbound rolling slowdowns and revisions along I-5 as crews work on the crossing
- Traffic control signs as well as WSDOT vehicles will guide vehicles safely through the work area
- There will likely be noise and lights from trucks and heavy machinery on adjacent streets.
Check back for project updates or contact us with questions.

Project overview
To increase electric reliability for customers in Skagit and Whatcom counties, we are rebuilding and reconductoring approximately 25 miles of existing transmission and distribution lines between Bellingham and Sedro Woolley.
Currently, the local electric system is prone to power outages due to limited capacity and aging infrastructure. The existing poles and conductors (wires) were built in the early 1960s and need to be replaced. Rebuilding these transmission and distribution lines with new, higher capacity wire and replacing the poles will strengthen the current system and reduce the frequency of outages for our customers in the area.
The overall project work will be completed in phases
All phases of this project include replacing the existing structures with new wood poles and new, higher capacity 115 kV transmission wire. It also includes replacing distribution wire as needed.
Phase A: Complete 2017
Alger to Belfast (4 miles)
Phase B: Complete 2018
Prairie Road near Belfast to the Norlum substation in Sedro Woolley (7.5 miles)
Phase C: Complete 2025
Lake Samish Park to Alger transmission line (6 miles)
Phase D: Upcoming spring 2026
Lake Samish Park to Bellingham (6 miles)
Phase E: TBD
Bellingham substation (0.5 miles)
Norlum substation to Sedro Woolley substation (0.5 miles)
Learn more
- Glossary
- Process Overview
- System Improvements Current Projects
Contact us
We welcome your questions and comments!
1-888-404-8773
MajorProjects@pse.com
